Overhang framing
“Rear eave, the overhang framing is in. Outlookers are about two feet on centre, hung off the LVL with hangers, and the overhang is about eighteen inches past the wall. Hurricane ties on every rafter on the south side.”
At the rear eave, the overhang framing was installed. The outlookers were spaced approximately 0.61 m (2'-0") on centre and supported from the LVL with hangers. The overhang extended approximately 455 mm (18") beyond the wall. Hurricane ties were installed at every rafter on the south side.