Guide Foundation walls

Foundation walls

What to say when you review foundation walls, from closing the forms to stripping and the top of wall.

Aerial view of wall forms set for a poured concrete foundation in a narrow city lot

Say it like this

Talk the way you would to a colleague on site. Below each recording is the note Neuveria writes from it. You review and edit every note before the report goes out.

Before closing the forms

You say

“North foundation wall, grid line A, one to five. Forms are up, wall's eight inches thick and about nine feet high. Vertical bars are fifteen M at sixteen inches, horizontals at eighteen, and the dowels from the footing are in. Ties look good, but there's no keyway at the footing joint on the west end. Contractor to add it before they close the forms.”

Neuveria writes

The north foundation wall at Grid Line A, between grid lines 1 and 5, was reviewed. The forms were installed for the 205 mm (8") thick wall, which was approximately 2.74 m (9'-0") high. Vertical 15M bars were installed at 405 mm (16") spacing, horizontal bars were installed at 455 mm (18") spacing, and the footing dowels were in place. The ties appeared satisfactory; however, no keyway was provided at the footing joint at the west end. The contractor is to provide the keyway before closing the forms.

Honeycombing after stripping

You say

“Forms are stripped on the east wall. There's honeycombing at the bottom near grid three, about three feet long and a foot high, maybe an inch deep. Tie holes aren't patched yet. Contractor to send the repair method before patching anything.”

Neuveria writes

The forms had been stripped from the east wall. Honeycombing was observed at the bottom of the wall near Grid 3, approximately 0.91 m (3'-0") long, 0.30 m (1'-0") high, and 25 mm (1") deep. The form-tie holes had not yet been patched. The contractor is to submit the repair method before undertaking any patching.

Top of wall and anchor bolts

You say

“South wall, the top of wall at the southwest corner is about an inch low compared to the drawings. Anchor bolts are at six feet on centre, but three are missing along the garage door side. Contractor to confirm the elevations with the surveyor and add the missing anchors.”

Neuveria writes

The top of the south wall at the southwest corner was approximately 25 mm (1") lower than indicated on the drawings. Anchor bolts were installed at 1.83 m (6'-0") on centre; however, three were missing along the garage door side. The contractor is to confirm the elevations with the surveyor and install the missing anchor bolts.

See it with your own projects

A 20-minute call where we walk through a real report from start to finish, or watch the 13-minute video first.

Book a demo