Pump and placement
“Pour on the main floor slab today, about forty-five cubes of thirty-two MPa with five to eight percent air. Pump truck set up on the street side. They started at seven thirty and finished around eleven. Placed in two lifts, vibrated well. Slump at the truck was about four inches.”
The main floor slab was poured on the day of the review using approximately 45 m³ (59 cu. yd.) of 32 MPa (4,600 psi) concrete with 5% to 8% air. The pump truck was set up on the street side. Placement commenced at 7:30 a.m. and was completed at approximately 11:00 a.m. The concrete was placed in two lifts and was well vibrated. Slump at the truck was approximately 100 mm (4").